Construction on the new high school, Phase I of the Campus Mita project, began in February of this year. The first main objective was to complete the foundation by the end of March. It is now 100% complete which means we are on time according to our construction calendar. Our next objective is to finish the structure for the first level (columns and slab) by mid-June. We are working on it now and on a good path to completing it by that date. After the first floor is finished, we will continue with the second floor, including columns and the roof. We hope to complete the structure of the main building by the end of July, approximately six months from the start of construction. Overall construction of Phase I is scheduled for completion in February 2024.